|
This brief introduction tells the story of how the temple project was
conceived and also of the community spirit and immense effort culminating
in its successful completion
The Old Temple
The old Swaminarayan temple in Vaughan Rd has been the centre of worship
since 1976. The increasing popularity and steady growth in devotees meant
a larger place was needed. Plans to re-build on the existing site were
prepared and it quickly became apparent that there were severe limitations
both in economic terms and the facilities possible within a small plot
size.
A building committee was set up to look for a suitable new site.
Sites in Harrow, Edgware and Kingsbury were earmarked due to its close
proximity of the devotees. Indeed two locations were reasonably advanced
but were lost to other purchasers.
Then the site known as Mark House on Westfield Lane, Kenton came to the
market.
The Site of the Current New Temple
Initial tentative enquiries looked promising, planning would of course
be a gargantuan task, During early discussions the Council were made aware
of the extreme difficulties at Vaugan Rd, indeed the officers were invited
during ‘Katha’ to see first at hand the problems faced by the community.
There were also able to appreciate the peaceful nature if the Swaminarayan
Worship.
Mark House has had a chequered industrial past, from the metals works
to an ice cream factory and it would appear now to have found a rightful
home.
The existing building appeared to be in a reasonable condition. Refurbishment
and conversion of the building was considered. Whilst the structure was
sound, architecturally to create an aesthetically pleasing temple would
be prohibitive on cost grounds alone. The shell and the ground floor would
also require thermal upgrading. Re-building seemed to provide the only
viable solution.
The Current New Temple
Draper Neal Associates were appointed as Architects who worked closely
with the building committee and the Harrow planners in preparing plans
for the new temple. The scheme was revised a number of times to meet the
Council’s stringent car parking and planning regulations for a public
building. Great efforts were made in explaining the need, it use and the
proposed activities to the local residents and the Harrow Planners and
Councilors. A basement car park was introduced to alleviate the problems
associated with the car parking. Through great resolve, self-belief and
regular prayers at the old temple planning permission was duly granted.
The architects brief was to create a temple, which would blend the use
of natural stonework typical of temple architecture in India and the brickwork
much used. The stone sikhars entrance domes from Rajastan and the curved
stone window surrounds and corner quoins from Lancashire appeared to give
the right balance
Following planning approval the scheme was developed for construction
by the Architect, Peter Neal and the structural Engineer, Khimji Lalji
Pindoria. Total sums of architectural and 20 structural drawings were
proposed backed by structural calculations for the sikhar supports, basement
concrete walls, floors and the steelwork frame. For the project of this
size full Bill of Quantities prepared were prepared by Clarke Associates
together with the Tender Contract Documents.
Tenders received for the full scheme were in the region of £1.6 million.
By nature Temples have a unique style of finishes and with the available
expertise within the community it was felt advantageous to split the contract
in two stages.
Stage 1 Shell Contract
Stage one, therefore comprised the shell and was carried out by Contractors
Jarvis of Harpenden and included foundations, basement and ground floor
concrete box, perimeter brickwork, structural steelwork frame by Promet
Technology (a community member company), composite metal deck concrete
roof and floor of the accommodation block together with the utility services
and drainage works. The duration this phase was September 1994 to September
1995.
During the course of the works a further planning permission was obtained
to create a 3m wide shoe rack and circulation area at the main entrance.
Stage 2 The Fit Out and Finishing
This stage forms than half the remainder of the works. An overall program
of the works was prepared with the assistance of Laxmanbhai Construction
as the main fit out contractor. After a slow start the momentum was built
up and maintained until completion. Services of the architect and the
structural engineer were retained.
A new Construction team was set up with trade discipline representatives
embracing the expertise and knowledge within the community. From weekend
working at the early stages, as the momentum built, the work progressed
on a daily basis with some volunteers taking odd days off work to complete
essential items and prepare for the follow on trades. Anticipated savings
due to volunteer labor, purchasing materials competitively, material donations
etc. is in the region of £500,000. The main trades are described here.
Electrical Works: From scheme
architectural layout the in house team developed the design to integrate
the capacity, selection of lights by Taison Lighting at competitive prices
and phased operation for optimum use. Internally some 35000m of cabling
supply power to 300 luminaires. External lighting includes lighting columns
and special effects to sikhars and entrance domes.
Heating & Plumbing: Similarly heating, plumbing and drainage to
the accommodation block, kitchens, w.c’s were designed and installed by
the in house volunteer team. The original tender proposals were greatly
improved to suit the projected usage of facilities. These included 6 No.
boilers, two for prayer hall two for accommodation block and two for the
kitchen. Additional ceiling mounted booster heaters are installed at ceiling
level.
Floor Heating: This specialist item was carried out by specialist
Durabella flooring. This form of heating is common in Europe and is becoming
increasingly used in the UK. A visit to the Japanese Museum of Art was
made to see where similar system has been installed, to see the system
in operation. The heating pipes being bonded to the flooring serves a
dual purpose at a considerable reduction in both installation, maintaince
and operating cost when compared to the high level ceiling system.
Mechanical Ventilation: For the size of the hall and the stringent
ventilation requirements under building regs. Pearce Associates were engaged
to design the system. Air conditioning was considered to be too costly
and maintenance intensive. The system selected essentially brings in fresh
air into the hall via heat exchangers through inlet ducts. Return outlet
ducts extract stale air from the hall to the atmosphere. The system was
designed and developed for installation by FM Strategic.
Carpentry: All joinery work has been carried out by the volunteers
with great assistance from Vascroft Contractors who made available their
workshop and even provided manpower for the more difficult tasks. Curved
window frames had to be made in the workshop and initiatives of the joiners
led to improvement of the design to a Georgian style. Other new ideas
include wall paneling, wood flooring and ceiling finishes and elaborate
covings. Main doors and the ‘sihasans’ were made in India.
PA and Security System: The security system provides a full alarm
system linking doors, windows and external door entry points with linked
cameras. Provisions also exist for extending the system. All designs were
carried out in house.
An extensive PA system has been designed in house. Special audio balconies
were added to form main switch rooms. The system has been designed to
serve three main purposes and includes 400m of cabling serving 50 speakers.
1) Everyday use through 35 No.ceiling speakers located in main hall, all
rooms, kitchens and wc’s; 2) Utsov use with the provision of 1000 watt
column mounted speaker system for live stage and music programmes; 3)
Announcements with controls from switch room in hall through floor junctions.
Sikhars and Entrance Domes: The work to the sikhars by the dedicated
team has been exemplary considering the state of the stone, which was
damaged in transit. The works took 2 months and included an ingenious
lifting gantry, which was fixed to the tower steelwork and allowed complete
rotational movement aiding positioning of stones with ease and safety.
Additional matching stonework patterns, to moulds specially made on site,
were cast to add a finishing touch to the stonework band along the front
elevation.
Plastering: This element of the work throughout the whole building
was carried out by the team of five plasterers resulting in consistent
finish. They were always available even when their finished work was subsequently
cut for services. The finished product reflects the quality and the effort
of the put in.
External Works: The external works, roads and landscaping always
give the building a sense of completion. In this respect the efforts of
young and old in planting shrubs, laying block paving, kerbs and general
external tidying up cannot be underestimated.
Nilkanth Hall Extension
For several years the devotees of the Shree Kutch Satsang Swaminarayan
Temple (London), Kenton, Harrow, strived to advance the education of younger
members and provide additional community facilities to complement the
devotional and spiritual fulfilment the Temple had successfully achieved.
The management committee consulted with various specialists including
planners, architects, Structural and services engineers, surveyors and
other building consultants and concluded that the construction of a 1st
floor extension to the Temple would provide a solution to the increased
demand for facilities and educational services. Once again we enlisted
the services of Draper Neal Associates to assist with the design and consultation
process. Once official planning consent had been granted by Harrow Council
the structural shell work was competitively tendered and contract awarded
to Laxmanbhai Construction to match the existing brickwork and decorative
stonework to maintain the aesthetically pleasing look of the Temple. The
beautifully crafted sandstone Shikars would remain as the show piece of
the skyline and therefore, the new construction was set back from the
front line of the building.
Once the shell work had been completed, the construction site was opened
up to the patiently waiting voluntary services teams comprising of carpenters,
electricians, plumbers, masons, plasterers and decorators. Just as had
been witnessed ten years prior, there was a buzz of anticipation as gradual
progress was made to fit out the new hall. The building committee maintained
an ever watchful eye on progress and enlisted the services of many volunteers,
young and old to join in the spirit and opportunity of cooperation.
With thousands of metres of cables and pipe-work being run to accommodate
a variety of services the progress became evident when the suspended ceiling
complete with air conditioning and air handling units was finally installed.
The building committee opted to provide a fresh look through utilising
natural stonework to highlight the walls and floors. Huge crates of marble
slabs were imported from India and China along with polished floor tiles.
In a very short space of time the marble and flooring were installed and
the unique splendour became self evident.
The carpentry team had spent time preparing doors and frames in workshops
which would become highlighted by the exquisite lighting scheme installed
which create an immediate impact. The audio visual systems were also installed
whilst the plumbing team fitted services in the kitchen area and fitted
out the washrooms. Once the entrance doors at the head of the stairs were
completed the hall had a feeling of completeness. The newly constructed
hall was named Nilkanth Hall thus continuing the timeline of our Supreme
Lord Swaminarayan.
Initial concerns over the ambitious timescale of the project were once
again proven to be unfounded as the generous and tireless voluntary service
of the devotees delivered on its promise and has provided a facility that
will be enjoyed by all generations and for many years to come.
It has taken over 4 years from initial planning to the completed project
which has been achieved due the tireless support of the temple Volunteers,
associated firms of suppliers, contractors and professional consultants
and installers of various trades.
The official opening of the Nilkanth Hall was performed during the Temple’s
10th Anniversary Celebrations on Tuesday, 26th December 2006 by His Holiness
Acharya Koshalendraprasadji Maharaj of Ahmedabad and will mark another
milestone in the achievements of the Shree Kutch Satsang Swaminarayan
Temple, (London), Kenton, Harrow towards the fulfilment of Lord Swaminarayan’s
principle to propagate education and provide service to devotees along
with a congenial place of worship.
|
|